A master planned development by Pointcorp and Dahua Group, Amity will be part of an expanding community, with lush green parklands, pathways and quality homes. The project is being completed in 10 stages and will ultimately consist of 467 lots.
Amity is a pioneering development in the Narangba East area.
RMA has been engaged to provide extensive civil, traffic and stormwater services from pre-DA to construction this 10 stage, 467 lot project in Moreton Bay Regional Council area. During the DA process, Council developed new road planning documentation, not tabled in due diligence pre-lodgements. This new planning required road resumptions and significant widening and vertical changes to the existing road.
Through a series of workshops with council, we were able to negotiate a position that delayed the external traffic works. This allowed initial stages of the development to proceed whilst deferring trunk water relocation costs.
Our civil team also coordinated a 1.25km rising sewer main that transversed through brownfield corridors, requiring extensive coordination with state authorities.